Closed

Little Malop Street Bridge - Design and Supply

Tender ID: 278090


Tender Details

Organisation:
Tender #:
T1700003  
Status:
Closed
Publish Date:
16 July 2016
Closing Date:
5 August 2016

Tender Description

⁠⁠⁠The City of Greater Geelong invites tenders closing 2.00 pm, Friday 5 August 2016 from experienced contractors to design and supply a pedestrian and cycle bridge across the Geelong-Warrnambool railway in Little Malop St Geelong.

Bridge design and construction shall be undertaken having regard to the requirements detailed in the Brief, the site conditions and shall be in accordance with all relevant Codes and Standards and the recommended codes of practice.

The bridge shall comprise of a single span over the rail corridor which conforms to the clearance requirements and technical specifications for the relevant authority(s) and the design criteria outlined in the documentation available here to download.

Works will include but will not be limited to:
1. Design of a new Pedestrian and Bicycle Bridge and ancillary works including public lighting and incorporation of service requirements.
2. Engineering certification of bridge design and as-built construction.
3. Obtaining final approvals for the design and construction as required to enable construction works to proceed.
4. Identification, proving and documentation of existing services that are required to be relocated or modified to facilitate bridge construction, including correspondence with relevant service authorities.
5. Offsite construction of bridge structure, as designed, to enable installation within the available rail closure windows.
6. Delivery of bridge structure to site, including traffic management, Occupational Health & Safety and Construction Environmental Management as outlined within the Principal's Conditions of Contract.

It is anticipated the assignment will be appointed by 12th August 2016 with the project to commence 15th August 2016.

The new bridge structure is to be installed during the November rail shutdown period. Accordingly the following deliverable timelines apply:
* Preliminary design drawings 30th August 2016
* Certified design drawings 15th September 2016
* Rail Authority approval to structure 15th September 2016
* Bridge Supply to site 16th November 2016

The Rail Authority have advised that shutdowns of the Geelong Warrnambool line are scheduled for 20 August 2016 and 19-20 November 2016.

For tender further assistance contact Graeme Kemp 03 5272-5033.