Tender Description
2.1 Background
• The Outcome sought is building alterations and upgrades to make Block G more functional and more connected to the adjacent buildings and the Sports fields in line with the school’s teaching requirements.
• The building’s use has evolved over time and is no longer 100% fit for purpose and these improvements will extend the useability of the Block into the future.
• There may be a requirement for phasing and/or staged handover of the project, this will be discussed at the mandatory site visit.
• Asbestos has been identified in the building and a Management Survey was carried out in 2020 by BluBeez Environmental. Asbestos removal is to be included in the works to the MOE guidelines and standards.
• Project consultants are:
o Project Manager: WSP – Roger Allsopp
o Lead Designer: Bishops – Aaron Thomsen
2.2 Required solution (method and approach)
a) The Contract Works required are: 3 separate stages of building alterations and upgrades to make Block G more functional and more connected to adjacent buildings and the Sports fields.
Overview: Demolition of selected walls and construction of some new walls to change the layout of the building. Installation of several ranch sliders to improve indoor/outdoor flow. Building covered decks for Outdoor learning opportunities with stairs/seating on the outlook to the sports fields. Relocation of services where required to suit.
• Nature of the Works is: (to be read in conjunction with draft drawings):
• Removal of Asbestos present as per the Asbestos Management Survey Report conducted in 2020 by BluBeez Environmental.
• Stage 1 – Rooms 8 and 9:
-Replacement of existing windows with stacker doors.
- Construction of deck with stairs and roof over between rooms 8 and 9 and to the east of room 9.
- Replacement of floor coverings
• Stage 2 - Room 10:
-Replacement of corner windows with stacker door and sliding window.
- Construction of deck with stairs and roof over to the east and south of room 10.
- Replacement of floor coverings
• Stage 3 – Room 11 and Music room:
- Replacement of existing window with stacker door.
- Replacement of floor coverings
- Installation of new Heat pump to Room 11
- Remove wall to west end of room 11 to link it to the music room
- Construct new wall between Room 11 and music room to re-apportion space between the 2 areas.
- Relocate existing sink and re-connect to existing services.
- Replace floor coverings
Location
Category
Waste Management : Asbestos Removal
Building Products & Materials : Doors & Windows & Glass : Floor Coverings
Building & Facility Construction & Maintenance Services : Building & Facility Maintenance & Repairs : Commercial & Industrial Construction Services : Partitions & Walls & Ceilings : Roof Plumbing
Civil Construction Services : Demolition & Removal