Killarney Gap Road Clearing & Concrete
Tender ID: 632069
Tender Details
Tender Description
This Tender is invited by the Issuer.
Overview
Gwydir Shire Council is seeking quotations from suitably qualified and experienced contractors to undertake clearing, drainage, rock protection, and concrete works at various flood damage sites along Killarney Gap Road. The works form part of Council's flood restoration program and are to be completed no later than 31 December 2026.
Scope
The Contractor shall provide all labour, plant, equipment, supervision, materials, traffic management, and incidentals required to complete the works described below.
Site DM01904, Causeway Clearing Works
- Remove stored debris from around the causeway
- Clear deposited material from the floodway and drainage paths as required
- Remove all spoil and waste material from site
- Dispose of all material at a lawful location at the Contractor's expense
- Reinstate any areas disturbed by the works
Site DM02352, Rock Protection Works
- Supply and install woven geofabric
- Supply and place D50 300mm rock protection
- Reconstruct damaged embankment areas as required
- Trim and shape completed works
- Rock protection shall comprise D50 300mm rock
- Geofabric shall be woven geofabric
- Gabion rock fill shall comply with Austroads ATS5150 requirements
Site EW00738, Drainage and Concrete Works
- Install drainage pipework and associated works
- Construct concrete protection works
- Reinstate surrounding road formation and drainage infrastructure
- Concrete shall achieve a minimum compressive strength of 40MPa
- Provide a concrete strength test report upon completion
Site DM01915, Concrete Apron and Protection Works
- Supply and place D50 300mm rock protection where shown
- Construct a concrete apron and associated protection works
- Reinstate disturbed areas
- Concrete shall achieve a minimum compressive strength of 40MPa
- Concrete apron thickness shall be a minimum of 100mm
- Provide a concrete strength test report upon completion
Traffic Management
- Provide traffic control at all work locations
- Submit a Standard Road Works Traffic Management Plan to Council for review and acceptance prior to commencing works
- Undertake all traffic management activities using appropriately qualified personnel and in accordance with applicable road safety requirements
Contractor Requirements
Tenderers shall demonstrate:
- Relevant experience undertaking similar civil construction, flood restoration, drainage, or road works
- Access to suitably qualified personnel
- Availability of appropriate plant and equipment
- Capacity to complete the works within the required timeframe
Contract Terms and Conditions
- Works are to be completed no later than 31 December 2026
- Council's Contract Manager for these works is the Project Manager, Sujan Patel
Location
- Road: Killarney Gap Road
- Map: View on Google Maps
Location
Category
Building Products & Materials : Aggregates : Geotextiles : Quarry Products
Building & Facility Construction & Maintenance Services : Concreting
Civil Construction Services : Civil & Earthworks (General) : Demolition & Removal : Road & Streetscape Construction & Maintenance : Stormwater Harvesting & Drainage Construction