Closed

Water Bore Drilling - Hemi Gold Project

Tender ID: 628498


Tender Details

Tender #:
-  
Status:
Closed
Publish Date:
13 October 2026
Closing Date:
22 October 2026

Tender Description

⁠⁠⁠Overview

Northern Star Resources Ltd (WA) intends to engage an experienced and reputable water bore drilling contractor to carry out the procurement, including supply of all consumables, construction and commissioning required to deliver the water and monitoring bores for the Hemi Gold Project.

Scope

The Project water bore drilling scope, as an overview, includes the following. It should be noted that the below details are preliminary and are subject to change pending further investigation.

Production Dewatering Bores

  • Up to 40 production dewatering bores within the mining pit areas
  • Dewatering bores drilled up to 65m deep
  • 12" bore diameter, a mix of steel and PN12 PVC casing
  • Conventional rotary mud drilling, sump construction, airlift, provision of annular concrete seal, concrete plinth and cap

Injection Bores

  • Up to 30 injection bores to the North and South of the Project infrastructure
  • Injection bores drilled up to 65m deep
  • 12" bore diameter, stainless steel screens and steel casing
  • Conventional rotary mud drilling, sump construction, airlift, provision of annular concrete seal, concrete plinth and cap

Monitoring Bores

  • Up to 45 monitoring bores
  • Monitoring bores drilled up to 65m deep
  • 2" bore diameter, PN12 PVC cased
  • Conventional mud or RC drilling, sump construction, airlift, provision of annular concrete seal, concrete plinth and cap

Location