Greatland Pty Ltd (WA) is seeking a contractor to undertake the Bulk Earthworks Construction package (CO010) for the Havieron Project, a brownfields gold-copper development. This is a critical early phase construction package focused on creating a stable foundation for buildings, roads and infrastructure at the project.
Scope
The bulk earthworks involve site preparation, drainage and environmental measures, large-scale excavation, cut and fill operations, filling, grading, and compaction to prepare stable, level, and technically compliant building pads. The scope covers the following areas:
Havieron Construction Pads
- Mine Infrastructure Area (MIA)
- Portal Area adjacent to Box Cut #1 (Chiller Plant Pad)
- Water Pump Station
- Corridor clearing for 33kV overhead line and 33kV/132kV Substation pad
- Blind Bore 4B Construction Pads (including Paste Plant sand storage pad, Refrigeration Plant pad, Substation pad and 9,790 m3 Catchment pond)
Havieron Internal Roads
- MCC2, Paste Plant Access Road, approximately 2.80km
- MCC1, Village Access Road, approximately 1.52km
- MC13, ROM P1 and MIA Access Road, approximately 2.02km
- MCP1, ROM P1 Access Road, approximately 530.0m
- MCM1, MIA Access Road, approximately 271.0m
- MCM2, MIA Access Road, approximately 172.0m
Key Characteristics: Bulk Earthworks for Infrastructure and Building Pads
- Survey and setting out work and site preparation
- Earthworks, including clearing, grubbing, topsoil removal, mass excavation, cut and fill, embankment construction, compaction, spoil handling, and winning and hauling fill material
- Borrow pit establishment and management
- Erosion and sediment control
- Surface water and groundwater control
Key Characteristics: Civil Works Associated with Road Construction
- Stormwater drainage
- Earthworks, including clearing, grubbing, topsoil removal, mass excavation, cut and fill, embankment construction, compaction, spoil handling, and winning and hauling fill material
- Borrow pit establishment and management
- Pavement construction
- Bituminous surfacing
- Erosion protection
- Signage and line marking
Instructions to Tenderers
Specific scope requirements will be communicated to suitable contractors via an Invitation to Tender.