Tathra Wind Farm is a proposed hybrid power generation facility, to be constructed in stages up to:
- 140 Wind Turbine Generators (WTG), up to 1,000 MW
- Solar energy, up to 500 MW; and
- Battery Energy Storage System (BESS), up to 500 MW.
TTWF1 is planned to be a hybrid facility of approximately 250 MW installed capacity of wind, and a 250 MW 8-hour BESS.
Synergy is seeking to undertake a competitive sourcing process to engage providers for the following high-level requirements:
- As Owner’s Engineer provide advice and support to the Owner in relation to a number of engineering project matters, during the development and delivery phases of the project; and
- As Project Delivery Partner provide ongoing project support during the delivery phase of the project, across a variety of engineering project management requirements.
Synergy encourages all interested parties for the requirements to register by emailing: TathraPDEOI@synergy.net.au
All registered parties will be invited to respond to the Synergy Expression of Interest (EOI) document for the procurement process. The EOI has the following indicative timelines:
- EOI registration period from 26 May 2026
- EOI document release date 2 June 2026
- Closing date for EOI responses 18 June 2026