Awarded

Tender - St Vincents Road new SUP Construction and Road Upgrade

Tender ID: 598273


Tender Details

Organisation:
Tender #:
OSI - 04/2025  
Status:
Awarded
Closing Date:
26 November 2025
Closing Time:
05:00 PM (Australia/NSW)
Awarded Date:
19 February 2026

Tender Description

⁠⁠⁠Overview

Lane Cove Council is inviting submissions from suitably qualified contractors with proven experience in civil infrastructure works to undertake the upgrade of St Vincents Road, between Gore Street and Bob Campbell Oval in Greenwich.

Scope

The scope includes:

  • Construction of a new shared user path (SUP)
  • Road upgrades to accommodate the SUP and provide marked on-street parking
  • Upgrades to stormwater infrastructure, including installation of new pipes and pits
  • All associated minor civil works required for full project completion

Contractor Requirements

  • Suitably qualified contractors with proven experience in civil infrastructure works
  • Works must be carried out in accordance with the project specifications, detailed design plans, relevant Council Standards, and applicable Australian Standards
  • Where subcontractors are engaged, they must be engaged under the contractor's role as Principal Contractor

Information Requested

A Bill of Quantities (BOQ) is provided, listing item descriptions and units of measurement. The Quantity column has been left blank for the contractor to complete based on the supplied detailed design plans.

  • Contractors must review the design drawings and determine and enter the required quantities for each BOQ item
  • If an item is not required, the quantity field may be left blank or marked as "0"
  • Any essential work items not included in the BOQ must be listed under "SCHEDULE H – Any Other Unaccounted Miscellaneous Works"
  • Pricing may be included based on subcontractor quotes, provided those subcontractors are engaged under the contractor's role as Principal Contractor

Contract Terms and Conditions

  • Works are scheduled to commence in mid to late January 2026
  • Project completion is targeted for mid-June 2026

Location

  • Road: St Vincents Road, between Gore Street and Bob Campbell Oval, Greenwich
  • Map: View on Google Maps

Location

New South Wales   :   Sydney  