Tender Description

Provision for new wash down bay and two (2) structures at the RoadTek Depot - Samuels Rd Bundaberg

Approvals

  • Plumbing approval (plumbing permit) is required from Bundaberg Regional Council
  • Development assessment/approval is required from Bundaberg Regional Council.

Equipment

  • A sediment trap/sump is required to settle out dirt/debris and must be fitted with a screen/grate/arrestor to remove solids such as rags/packaging.
  • Supply and install of a rainwater tank, to be supplied from the roof of the washdown bay to supply water to the pressure washer.
  1. Rainwater tank would require a flow meter installed to capture volumes used.
  2. A ‘switch’ connection would also be required to switch to Council’s water supply if no rainwater available.
  • Oil water separators shall have a capacity greater than the peak hourly flow (L/hr).

Design

  • Approx size of washpad:
  1. 7m wide
  2. 11m long
  3. 6.5m high (roof)
  • Stormwater and wastewater must be kept separate, so the wash bay design must consider this.
  • Required to be roofed and roofing is to overhang the bund by 25% of the open wall height.
  1. Alternatively, enclosing the wash bay may be an alternative to overhanging roofing.
  • Bund of at least 100mm high (or speed hump of 75mm high) is required on all sides to prevent entry of surface stormwater into the wash bay.
  • Floor is to be impervious (e.g., preferably concrete).

Material Handling

The following products will need treatment/management from the wastewater generated from the wash down bay:

  • Hydrocarbons (oil/diesel)
  • Dirt/debris
  • Cationic emulsion (emulsion spills 1-2 times per week, generally maximum volume is 500mL).
  • Kerosene (used for emulsion at 50% of spill volume – up to 250mL).
  • Herbicides (assuming negligible amounts, if any at all. The presence/absence of herbicides will need to be confirmed with the successful contractor to ensure waste water is effectively treated).

Discharge to holding tank

  • Requires regular pump outs of holding tank by a licensed regulated waste transporter (waste will be regulated under code J120 – oily water).
  • Holding tank will require a manhole or similar opening to enable sucker truck access for pump outs.
  • Holding tank should meet the relevant Australian Standard (e.g., AS/NZS 4766 for polyethylene storage tanks).
  • Pump outs will be carried out by a licensed regulated waste transporter (e.g. Cleanaway).

Additional Installations

Structure 1 – Covered Area Front

  • Design and construct roof structure to be located at the front of an existing shed
  • Utilising existing base
  • Steel/colourbond construction
  • Angle/guttering to support water flow into existing water tank.
  • Approximate size:
  1. 3.5m high
  2. 8.5m wide
  3. 6.4m depth

Structure 2 – Covered Area Side

  • Design and construct roof structure to be located at the side of an existing shed
  • Utilising existing base
  • Steel/colourbond construction
  • Angle/guttering to support water flow into existing water tank (if able).
  • Approximate size:
  1. 3m high
  2. 7m wide
  3. 4.9m depth 