2020-CTEQ-8210-30AS-0002

Scope of Work: Trial Pit - Resource Infill Drilling at the proposed Trial Pit area at the Sunrise Site.
* CLQ Owner: Luke Cox, Mining and Geology Manager;
* Start – February 2019;
* Duration - Approximately 1-month Site drilling work;
* Personnel – Up to 4 fulltime Site-based drilling contractors;
* Equipment – Truck or track-mounted Reverse Circulation (RC) drill rig and ancillary support truck and light vehicles;
* Logistics – Contract drilling personnel will reside at Syerston Station with caravan accommodation or commute from nearby Motel (Fifield, Trundle, Condobolin), ;
* Risks – Fire, fuel spills, machinery moving parts, road/traffic movements, fatigue.

This Scope of Work covers the required drilling coverage by the contractor including site locations, depths, sampling quality, operations etc.

* 3,500m of RC face-sampling hammer drilling at the Sunrise Ni-Co-Sc Site;
* Drillhole spacing with be approximately 10m x 10m pattern in an open farm field (Figure 1 below);
* Drillholes will be vertical and drilled to depths will vary between 30m to 50m below surface
* Sampling will be every metre and care needed to ensure no smearing of samples/results downhole