Provision of Cable Routes, Blown Fibre Ducts & Fibre Implementation
Tender ID: 307227
Tender Details
Tender Description
The PTA is undertaking a project to replace all Kingfisher Remote Terminal Units (RTU) along the Joondalup, Midland, Armadale and Fremantle lines with the Schneider M580 model RTU.
As a technical pre-requisite, Optical Fibre is required to the locations the M580 will be implemented to meet technical requirements, enhance reliability and align with industry best practice.
Phase 1 - Section 1 - Victoria Park to Kenwick (Includes Trial site in Cannington area) - 5.800km to 16.560km, Armadale Line:
* Provision of approved Safety Management Plan and other documentation in relation to mobilisation (See Book 4);
* Supply of blown fibre duct system with its associated parts/equipment;
* Supply of the required optical fibre cables;
* Supply of the required cable containment system (i.e. including pits and pipes) that will be suitable for installation of single mode optical fibre cables;
* Supply and install of the required undertrack crossings (or trenchless excavations);
* Supply of new location cases where required and associated parts/equipment (including concrete slab, earth rods, handrails, etc.);
* Pre-works site survey utilising existing completed surveys/design and protecting existing PTA services in all worksites;
* Undertaking topographical surveys prior and during the installation of undertrack crossings and provide methodology for PTA Track and Structures approval;
* Preparation, setup and reinstatement of lay down area;
* Vegetation clearing required for the cable and containment system installation works;
* Cable containment system installation. Tenderer to identify proposed methods for each location where new containment is required;
* Blown fibre duct installation by utilising existing and newly installed cable containment system;
* Fibre cables installation (i.e. air blowing, splicing);
* Supply and installation of FOBOTs at location cases and Relay Rooms/Communications Rooms;
* Testing and commissioning of completed works with completed Inspection & Test Plan (ITP) documents (including Optical Time Domain Reflectometer (ODTR) testing for fibre cables from both cable ends);
* Provide hydro mulch finish in the area that requires revegetation;
* Undertaking final topographical surveys for development of ‘as constructed’ drawings and completing all related technical and safety documentation for trenchless excavations (refer to 8110-400-030);
* Production of redline drawings during construction; and
* Provide ‘as constructed’ drawings for the works completed under the Contract.