EOI Drill & Blasting Operations
Tender ID: 263072
Tender Details
Tender Description
This Scope of Works includes the establishment and demobilisation and operational management of four or more locations including of the provision of labour, plant and equipment required to undertake site Drill & Blast in accordance with but not limited to the TMR Project Specifications MRTS 51 and MRTS 55, and to the relative Australian Standards, and project specific environmental requirements.
It is anticipated the works will commence Mid 2016 at two locations the third and fourth location at the end of 2016. These times and location start dates can vary and are supplied as an indicative timeframe only.
The Project is divided in 3 sections as follows:
Eastern Section: Warrego Hwy East (CH 0) to TSRC Viaduct (CH 17,467)
Central Section: TSRC Viaduct (CH 17,467) to Boundary St. (CH 22,610)
Western Section: Boundary St. (CH 22,610) to Gore Highway Interchange (CH 43,010)
The approximate total M3 of material to Drill & Blast is 1.34 Million. The total M3 is dependent upon the final design. The tentative quantities in each location are broken down into the CUT locations below. The drill & blast locations and quantities are subject to ongoing geotechnical investigations being completed and design being finalised over next several weeks.
Location 1 CH: 7,500. Cut 10
Approximately 295, 000 M3 to Drill & Blast
Location 2 CH: 13,200. Cut 22/23
Approximately 695,000 M3 to Drill & Blast
Location 3 CH: 17,800 Cut 29
Approximately 150,000 M3 to Drill & Blast
Location 4 CH 21,900. Cut 32 /33
Approximately 200,000 M3 to Drill & Blast